After a brief work session at which they finalized the agenda for next week's regular board meeting, members of the Detroit Lakes School Board, administrators and staff set off on a two-hour tour of the district's summer construction projects with lead architect Brian Berg.

What they found was that, despite some minor weather delays, renovations and additions to Rossman Elementary, Roosevelt Elementary and Detroit Lakes Middle school facilities are on target and on budget so far.

WDAY logo
listen live
watch live

According to Berg, interior renovations to all three buildings should be complete by the start of the fall semester on Aug. 28.

"Classroom additions on the north ends of Rossman and Roosevelt are scheduled to be complete when students return from the holiday break after Jan. 1 of next year," he added.

"At this point they (contractors) are on track for that schedule," Berg said. "We will be able to fully firm that up in a couple months once we are out of the ground and enclosed on both sites."

Gymnasium additions to both sites are also slated for completion next year, though the new Rossman gym won't be ready for use until the start of classes in the fall of 2020.

Because construction of the Rossman classroom addition involved removal of the existing, portable classrooms that had been in use for more than 40 years, and they also needed a gym, some temporary space had to be found - and the National Guard Armory stepped up.

Until the additions are complete, Rossman students will be using the gymnasium and classrooms in the Armory - which is conveniently located right across the street from the school - for their music and physical education classes.

"The armory space will be used for the entire school year," Berg said.

One other change brought about by the construction at Rossman was the relocation of the playground. Because the existing playground site was part of the area slated for the gymnasium addition, the playground has been permanently relocated to the southwest corner of the site, and will thus be ready for use this fall.

Renovations and additions at Detroit Lakes High School, which will account for more than half of the $50 million overall project, are slated to begin next summer, with completion in 2021. Bids for the high school improvements will be let later this fall.